Lake Williams Dam Project

The New Sluice Gates

The new sluice gates have been installed at Lake Williams Dam.

The new sluice gates have been installed, and the contractor is currently working on the stems that will allow the gates to be operated from the top of the dam.

The interior of the outlet pipe has been cleaned and dried, and the contractor has started applying the lining material.