Lake Williams Dam Project

A public meeting to discuss project updates and upcoming construction activity will be held on Tuesday, March 1, 2022 from 6:30-7:30 PM at the Goodwill Fire Company at 1 South Main Street, Jacobus, PA 17407. Members of the public are welcome to attend.

Click here to view a video story produced by the York Daily Record on the Lake Williams Dam project.

Lake Williams Dam Project Press Release, November 1, 2021

Lake Williams Dam Project FAQ’s.

January 14, 2022:

Our contractor completed the temporary access road work on January 14, 2022. The site is now in hibernation for the rest of the Winter until early Spring, when demolition work on the bridge will commence.

November 3, 2021:

Preliminary site construction activities to install an access road on the south side of the Lake Williams Dam in Springfield Township started on November 3, 2021. This stone-based road will provide equipment access from the end of Water Street to the downstream of the dam area. The road will be used by and accessible only to York Water and contracted heavy construction equipment.

October 6, 2021:

   

Lake Williams reservoir has been lowered about 6 feet, in accordance with Fish and Boat Commission requirements. This lowering is necessary in order to start the planned work on the Lake Williams Dam. In 2022 and most of 2023, the Lake Williams reservoir will need to remain lowered for dam reconstruction. Because we can pull water for treatment from Lake Redman, your water supply and that of all York Water’s customers will not be affected by the temporary drawdown and construction at Lake Williams. Our investments in operational flexibility will allow us to continue to provide the same high-quality water that The York Water Company takes pride in delivering. However, we recognize that the temporary viewshed and appearance will not be typical.

April 9, 2021:

Geotechnical investigations on and around the dam have been completed. Design plans for renovation of the dam and spillway are being prepared by our engineering consultant. The Water Street Bridge remains closed to vehicle traffic.

December 8, 2020:

   

 

 

 

 

 

 

 

 

 

 

Geotechnical investigations are being conducted on and around Lake Williams Dam. This work is part of a major renovation project to enhance dam safety for the downstream public. York Water estimates the site investigations will continue to the end of 2020.

January 16, 2020:

York Water is in the midst of a three-phase dam improvement project that will span over several construction seasons. Phase 1 work has been completed and Lake Williams’ gates are now up, and the lake is at full capacity. We are awaiting DEP approval for Phase 2 work to reconstruct the dam’s spillway to current design standards. Once approval is granted, we will need to lower the water level 20 feet to complete the spillway construction work.

November 1, 2019:

Lake Williams is “full” to the bottom of the bascule gates. The gates are in the down position and will remain in the down position until after the Lake Williams Project is complete. The gates are 4′ high, so Lake Williams is 4′ below normal full elevation.

September 12, 2019:

The crossing on Water Street is now open to pedestrians, bicycles, and horses. The road remains closed to motorized vehicles.

Lake Williams is back open to boating and fishing. York Water has been working with the PA Fish and Boat Commission to begin the process of restocking the fish in Lake Williams.

July 3, 2019:

June 10, 2019:

The new sluice gates have been installed, and the contractor is currently working on the stems that will allow the gates to be operated from the top of the dam.

The interior of the outlet pipe has been cleaned and dried, and the contractor has started applying the lining material.

October 17, 2018:

September and October had more precipitation than usual, but the drawdown of Lake Williams continues. The Water Street Bridge remains closed until further notice. Construction is set to begin by the end of October. The York Water Company thanks the public for their continued cooperation during this historic project.
Photo of Lake Williams In October 2018

As of September 7, 2018, Lake Williams is down 22 feet.

Photo of Lake Williams September 2018

As of September 4, 2018, Water Street is closed until further notice. Construction mobilization and activities will begin mid-September 2018.

Photo of Water Street closed for construction

Download Other Information About This Project: